The Park Service has asked American Whitewater to share the following Grand Canyon planning update. Of particular interest is that the Park has expressed an intention to select a preferred alternative in the draft EIS and that release of the EIS continues to be delayed from the originally scheduled release date this summer.
American Whitewater continues to work on this issue and track this project as we strive to work with the Park to fix the Waiting List. Individuals registering for a private boater launch permit in 2003 will not be able to receive their permit until 2029 under current management practices. We are in touch with the Park and working closely with our affiliate Grand Canyon Private Boaters Association (www.gcpba.org). More information about this issue and American Whitewater's work as a Top Issue of 2003 is available at http://www.americanwhitewater.org/archive/article/954/
October 21,
2003
From: Planning Team Leader, Colorado River Management
Plan
Subject: Update on the CRMP Planning
Process
Grand Canyon National Park is making considerable progress in developing a Draft
Environmental Impact Statement for revising the park's Colorado
River Management Plan (CRMP). We have developed a full range of reasonable draft
alternatives (including the current situation which is
the No Action alternative), which is now undergoing preliminary
impacts analysis.
The planning team has carefully considered and addressed input including the
following:
- Extensive comments the park received during the public
scoping period in
2002,
- Input from the stakeholder workshops and expert
panels,
- Consultation with Native American
Tribes,
- Interagency
consultation,
- Provisions of the 2002 lawsuit settlement
agreement,
- Extensive data and other information gathered by the
planning
team, and
- Laws, policies, and principles guiding plan development
(on the CRMP
website at www.nps.gov/grca/crmp).
The next steps in the CRMP planning process will
include:
- Add mitigation measures to the alternatives, as necessary,
to
address any major impacts identified in the preliminary
impacts
analysis. The mitigated alternatives will then undergo
additional
impacts analysis. All of this is scheduled for completion in
early
November.
- Review the draft alternatives and draft impacts analysis,
make any
necessary changes, and select a preferred alternative. The
preferred
alternative will be the agency's proposal for a revised
CRMP; it may
be one of the draft alternatives, the No Action alternative,
or a
new alternative developed during the preferred alternative
selection
process.
- Publish a Draft CRMP/EIS for public review and comment
(after any
additional revisions and
analysis).
We will not know the exact timing for publishing and public review of the
Draft CRMP/EIS until the preferred alternative selection process has been
completed. Once that process is completed, we will announce the schedule
in a note to the CRMP email list, and on the CRMP website. When the Draft
CRMP/EIS is published, the park will issue a Notice of Availability
in
the Federal Register, a press release, and a note to everyone on the CRMP
mailing list. We have begun planning for extensive public
review
opportunities, including public meetings, and we will keep you informed
as we develop the
details.
Please send any comments or questions concerning this note or the process
to grca_crmp@nps.gov (please be sure to use an
underscore to make
grca_crmp). Thank you for your interest in Grand Canyon National Park and
the Colorado River Management
Plan.
Rick
Ernenwein
CRMP Planning Team
Leader
Photos:
http://www.americanwhitewater.org/photos/?photoid=2877
http://www.americanwhitewater.org/photos/?photoid=2100